Every spring the phone does the same thing. The evenings get lighter, someone stands in a narrow kitchen for the hundredth time, and they decide this is the year. They call in March hoping to start in April. For a new bathroom, that can sometimes work. For an extension, a loft or a whole-house renovation, it almost never does, and the reason has nothing to do with how busy any builder is.
It's the clocks. Planning applications, party wall notices and Building Regulations each run on their own timetable, and none of them start until someone has decided exactly what's being built. Start those clocks in winter and a spring start is realistic. Start them in spring and the build moves to summer, or autumn, without anyone doing anything wrong. This is how we'd use the winter months if the aim is builders on site by spring.
Work backwards from the start date
The runway in front of a project depends on what the project is. Inside the house, it's short. A new kitchen, a bathroom or a knock-through needs no planning permission on most terraces (we've set out what needs planning permission on a Victorian terrace separately), so the runway is a settled scope, a fixed price, Building Regulations for anything structural, and orders placed early enough for the things with long lead times.
Anything that changes the outside of the house is a different shape. A side return, a rear extension or a loft can need a full planning application, which has a statutory determination period of eight weeks once it's validated. Some single-storey rear extensions can go through the Larger Home Extension prior-approval route instead, which runs to around six weeks including the neighbour consultation. On a terrace there are also party wall notices, which carry their own notice periods under the Party Wall etc. Act 1996: two months for work to the party wall itself, one month for excavation near a neighbour's foundations. If a shared drain runs where the extension will sit, there's a build-over agreement with Thames Water as well.
Put those together and the arithmetic is plain. For an extension that needs planning, the gap between deciding to build and moving into the new room is usually five to seven months, which we go through properly in how long a renovation actually takes. For an April start, the application wants to be in by the end of January. For that, the drawings need to be done in January. For the drawings, the scope needs settling before Christmas.
November and December: decide what you're actually building
The most useful thing you can do this side of Christmas is decide what the project is. Not the finishes. The shape of it. There are usually three ways to get more from a terrace: open up what's already there, extend into the side return or the garden, or go up into the roof. We've written about each in opening up a Victorian terrace, extending a Victorian terrace and converting the loft of a Victorian terrace. They have very different runways. An internal remodel can often start within weeks of the price being agreed. An extension in a conservation area can't.
This is also the time to find out whether your street is in a conservation area or carries an Article 4 direction, because that single fact moves more of the timetable than anything else. Waltham Forest, Hackney and Haringey all publish their conservation area maps, and we check the designation for every house before we quote it.
And it's the time to talk to the neighbours. A party wall notice is a formal document with a statutory clock. A conversation over the garden wall in December, before any notice lands on the mat, is what turns that formal process into a form and a signature rather than two surveyors and a fee.
A first consultation belongs here too. Ours is free and lasts about an hour. We'll walk the house, tell you which permissions the project actually needs, and give you an honest view of the runway. If the room you want turns out to be inside the house already, we'll say so. It's usually the cheapest news we get to give.
January: drawings in, notices out
With the scope settled, the architect draws it and, for anything structural, an engineer calculates it. On a terrace that usually means steels: over a widened opening, across a side return, or in the floor of a loft. Those calculations go to building control, and the planning drawings go to the council.
Building Regulations offer two routes. A full plans application has the drawings checked before the work starts, with a decision due within five weeks, or two months if you agree to extend it. A building notice lets work start sooner, with compliance checked as it goes. On anything structural, we'd rather the engineer's details were approved before the steel is ordered than queried once it's in.
Party wall notices can go out once the drawings show what's being built. They don't have to wait for the planning decision, and sending them in January means the two-month clock is running while the council does its eight weeks, rather than starting after it.
February: fix the price, order the long-lead things
By February the drawings are settled enough to price properly. That means a written scope and a fixed price, not a figure per square metre. If you've got more than one quote, our guide to reading a builder's quote covers how to check they describe the same job.
Then the orders. Some things on a period house take longer to arrive than the build takes to reach them. Kitchen units made to order. Windows, especially timber sashes. A bespoke staircase for a loft. Joinery made to the room rather than bought for it. Reclaimed London stocks to match the house, which have to be found before they can be laid. Materials are agreed before they're ordered, and the earlier they're agreed, the less the programme depends on a delivery date.
What can happen over the winter itself
Winter is not a dead season for building. Inside the house it's a good one. Internal remodelling, joinery, kitchens and bathrooms go ahead regardless of the weather, and a house that's already being opened up in February is a house that will be finished by spring.
Some work is better waiting. Lime mortar doesn't like frost, so repointing and front elevation restoration are usually programmed for late spring and summer, when the mortar can cure properly. If your project is the outside of the house, winter is for the consent and the scaffold booking, not for the brickwork.
A full renovation can use the season in two halves. The internal structural work goes in over the winter, and anything external follows once the weather turns. We'd set that sequence out at the start rather than discover it in March.
Booking the builder
We take on three or four projects at a time. A start date only means something if the project before it finishes when it should, so we set start dates once the paperwork is in hand and the price is agreed, not before. That's not a reason to hurry. It's the reason the timeline given is the timeline kept.
What it does mean is that the order of things matters. Talking to a builder in December, while the scope is still forming, costs nothing and often saves a redraw. Talking to one in March, with drawings already submitted that nobody has priced, can cost a month.
When should I start planning an extension for a spring build?
Before Christmas, ideally. An extension that needs planning permission wants its application in by the end of January for an April start, which means drawings in January and the scope settled in December. From deciding to extend to moving into the room is usually five to seven months.
How long does planning permission take?
A householder application has a statutory determination period of eight weeks once it's validated. The Larger Home Extension prior-approval route runs to around six weeks. Validation itself can add time if the drawings or forms aren't complete when they go in.
Can building work go ahead in winter?
Inside the house, yes. Remodelling, kitchens, bathrooms and joinery are unaffected by the weather. Lime pointing and external brickwork are better left until the risk of frost has passed, so external restoration is usually programmed for late spring and summer.
Do I need planning permission before serving party wall notices?
No. Notices can be served once the drawings show what's being built, and serving them while the planning application is being decided means the two clocks run together rather than one after the other.